Announcement of Ministry of Housing and Urban-Rural Development of the People s Republic of China
-
Foreword
-
1 General Provisions
-
2 Terms
-
3 Basic Provisions
-
4 Hot Metal Pretreatment
-
4.1 Process Design
-
4.2 Powder
-
4.3 Process Equipment
-
4.4 Process Layout
-
5 Converter Steelmaking
-
5.1 General Process Design
-
5.2 Material Preparation and Supply
-
5.3 Process Equipment
-
5.4 Layout of Converter Steelmaking Shop
-
6 EAF Steelmaking
-
6.1 Process Design
-
6.2 Material Preparation and Supply
-
6.3 Process Equipment
-
6.4 Layout and Building of EAF Steelmaking Shop
-
7 Secondary Refining
-
7.1 Process Design
-
7.2 Material Preparation and Supply
-
7.3 Process Equipment
-
7.4 Process Layout
-
8 Slag Treatment
-
8.1 General Process Design
-
8.2 Converter Slag
-
8.3 EAF Slag
-
8.4 Slag from Refining and Residual Scrap from Casting
-
8.5 Slag from Hot Metal Pretreatment
-
8.6 Stainless Steel Slag
-
8.7 Process Equipment
-
8.8 Process Layout
-
9 Mechanical Repair and Laboratory
-
9.1 Mechanical Repair
-
9.2 Laboratory
-
10 Electrical Power
-
10.1 Load Classification and Power Supply
-
10.2 Power Supply and Distribution System
-
10.3 Reactive Power Compensation and Quality of Power Supply
-
10.4 (Distribution)Substation and Electrical Room
-
10.5 Power Supply and Distribution Facility and Electrical Drive
-
10.6 Power Engineering
-
11 Instrumentation
-
11.1 Selection and Design of Instrument
-
11.2 Measuring and Control Item
-
11.3 Power Source of Instrument
-
11.4 Instrument Protection and Safety
-
12 Telecommunication
-
13 Automation Control and Information-based Technology
-
13.1 General Provisions
-
13.2 Basic Automation
-
13.3 Process Control
-
13.4 Information-based Technology
-
14 Water Supply and Drainage
-
14.1 General Provisions
-
14.2 Water Quality and Requirement for Steelmaking Process
-
14.3 Water Supply System
-
14.4 Water Treatment Facility
-
14.5 Emergency Water Supply
-
14.6 Water Quality Stabilization
-
14.7 Makeup Water
-
14.8 Water Quality Analysis and Monitoring
-
15 Thermal Power
-
15.1 General Provisions
-
15.2 Waste Heat Boiler System for Converter
-
15.3 Waste Heat Boiler System for EAF
-
15.4 Thermal Power Facility for Secondary Refining
-
15.5 Steam Supply
-
15.6 Compressed Air Supply
-
16 Heating,Ventilation and Air Conditioning and Dedusting
-
16.1 General Provisions
-
16.2 Heating
-
16.3 Ventilation
-
16.4 Air Conditioning
-
16.5 Dedusting
-
17 Fuel and Gas
-
17.1 General Provisions
-
17.2 Converter Gas Cleaning and Recovery System
-
17.3 Gas Valve Station and Pipe Network
-
18 Building and Structure
-
18.1 General Provisions
-
18.2 Main Shop Building
-
18.3 Equipment Foundation
-
18.4 Process Platform
-
18.5 Building for Utility
-
19 General Layout and Material Transportation
-
19.1 Selection of Plant Site
-
19.2 Layout of Plant Area
-
19.3 Transportation
-
19.4 Greening
-
20 Safety and Environment Protection
-
20.1 Safety
-
20.2 Fire Protection
-
20.3 Environment Protection and Comprehensive Utilization
-
21 Energy Conservation
-
22 Engineering Pricing and Project Investment Consulting
-
22.1 Engineering Pricing
-
22.2 Project Investment Consulting
-
Explanation of Wording in This Code
-
List of Quoted Standards