GB 51171-2016 GB 51171-2016通信线路工程验收规范 英文: - 工标库
由工标库AI生成
查看更多
GB 51171-2016 GB 51171-2016通信线路工程验收规范 英文:现行
收藏
-
Foreward
-
1 General Provisions
-
2 Terms
-
3 Material Test
-
3.1 General Requirements
-
3.2 Single-drum Optical Fiber Cable Examination
-
3.3 Single-drum Cable Examination
-
3.4 Wire Pole Examination
-
3.5 Examination of Silicon-core Pipe and Accessories
-
3.6 Examination of Stranded Galvanized Steel Wire and Ironware
-
3.7 Joint Box and Splice Jacket Examination
-
3.8 Connector Examination
-
3.9 Distribution Frame Examination
-
3.10 Distribution Cabinet Examination
-
3.11 Examination on Microduct,Microduct Bundle,Microduct Cable and Microduct Accessories
-
3.12 Other Cable Line Material Examination
-
4 Cable Route
-
5 Earth Works
-
5.1 Excavation
-
5.2 Backfilling
-
6 Overhead Pole Line for Overhead Cable
-
6.1 Pole Erecting
-
6.2 Pole Extension
-
6.3 Pole Footing
-
6.4 Stay Wire
-
6.5 Bracing Pole
-
6.6 Pole Numbering
-
6.7 Overhead Suspension Wire
-
7 Laying of Optical(Electrical)Cables
-
7.1 General Requirements
-
7.2 Laying of Directly-buried Optical(Electrical)Cables
-
7.3 Installation of Overhead Optical(Electrical)Cables
-
7.4 Installation of Wall-mounted Optical(Electrical)Cables
-
7.5 Laying of Duct Optical(Electrical)Cables
-
7.6 Laying of Underwater Optical(Electrical)Cables
-
7.7 Leading-up of Optical(Electrical)Cables
-
7.8 Laying of Micro Duct and Micro Cable
-
7.9 Laying and Installation of Silicon-cored Plastic Duct
-
7.10 Manhole(Handhole)Construction of Silicon-cored Plastic Pipe
-
8 Cable Line Protection and Preservation
-
8.1 Built-in Pipe,Brick-Paving,Cover-board,and Cement Mortar Bag
-
8.2 Terrace Slope Reinforcement and Protection
-
8.3 Protection of Underwater Optical(Electrical)Cable
-
8.4 Protection of Pole Line,Stay Wire,Suspension Wire and Overhead Line
-
8.5 Protection of Silicon-cored Pipe
-
8.6 Stone Marker and Sign Board
-
8.7 Protection against High Power
-
8.8 Lightning Protection
-
8.9 Other Protection Requirements
-
9 Optical(Electrical)Cable Cross Connection Box and Distribution Device
-
9.1 Installationof Optical(Electrical)Cable Cross Connection Box
-
9.2 Installation of Distribution Device
-
10 Optical(Electrical)Cable Splicing
-
10.1 General Requirement
-
10.2 Optical Cable Splicing and Encapsulation
-
10.3 Splicing and Encapsulation of Electrical Cable
-
11 Optical(Electrical)Cable Lead-in and Termination
-
11.1 Installation of Optical(Electrical)Cable in the Equipment Room
-
11.2 Installation of Optical Cable Termination
-
11.3 Installation of Electrical Cable Termination
-
12 Optical(Electrical)Cable Test
-
12.1 Optical Cable Test
-
12.2 Electrical Cable Test
-
13 Preparation of As-built Documentation
-
14 Final Acceptance of Work
-
14.1 Follow-up Test
-
14.2 Preliminary Acceptance
-
14.3 Trial-run
-
14.4 Final Acceptance
-
Appendix A Single-drum and Whole-process Test Parameters for Copper-cored Plastic Cables
-
Appendix B Requirements for Earthing Resistance of Lightning Wire and Length of Extension Line(Underground Part)
-
Appendix C Requirements for Earthing Resistance of Optical(Electrical)Cable Suspension Wires and Other Facilities
-
AppendixD Original Erection Sag for Suspension Wire of Overhead Optical (Electrical)Cable
-
Appendix E Test Record for Repeater Section of Optical Cable Line
-
Appendix F Permissible Reduction Value of Air Plug Pressure
-
Appendix G Permissible Air Pressure Reduction of Plastic Cable in 24h
-
Explanation of Wording in This Code
-
List of Quoted Standards