中华人民共和国住房和城乡建设部公告
-
Foreword
-
1 Scope
-
2 Normative References
-
3 General Provisions
-
3.1 General Requirements
-
3.2 Basic Requirements for the Machine Train Construction
-
4 Preparations for Construction
-
4.1 Technical Preparations
-
4.2 Site Preparations
-
4.3 Unpacking Inspection
-
4.4 Foundation Inspection,Re-measurement and Surface Treatment
-
5 Overall Installation of the Machine Train
-
5.1 Installation of Supporting Plates and Shims
-
5.2 Installation of Baseplate in Position
-
5.3 Installation of the Machine Train in Position
-
5.4 Shaft End-to-end Distance Confirmation and Shaft Alignment
-
5.5 The Machine Train Grouting
-
5.6 Coupling Assembly
-
6 Gearbox Assembly
-
7 Axial Compressor Assembly
-
7.1 Assembling Procedure
-
7.2 Axial Compressor with Bearing House and Casing Separated
-
7.3 Axial Compressor with Bearing House and Casing Integrated
-
8 Assembly and Examination of Expander
-
8.1 Examination Prior to Expander Assembly
-
8.2 Assembly of Expander
-
9 Assembly of Motor/Generator
-
10 Auxiliary Facility and Piping Installation
-
10.1 Auxiliary Facility Installation
-
10.2 Piping Connection
-
10.3 Oil System Flushing
-
11 Running Test of the Machine Train
-
11.1 Preparations for Running Test
-
11.2 Running Test of Oil System
-
11.3 Mechanical Running Test of the Motor and Generator
-
11.4 Mechanical Running Test of Gearbox
-
11.5 Mechanical Running Test of Axial Compressor
-
11.6 Mechanical Running Test of Expander
-
12 Technical Documents of Construction Completion
-
Appendix A(Informative) Technical Characteristics of the Machine Train
-
Appendix B(Informative) Mono-indicator Alignment
-
B.1 Basic Procedures of Mono-indicator Alignment
-
B.2 Determination of Support Adjusting Quantity by Means of Graphing Method
-
B.3 Determination of Support Adjusting Quantity by Means of Calculation Method
-
Explanation of Wording in This Code