Foreword
-
1 General Provisions
-
2 Terms
-
3 Basic Requirements
-
4 SC Platform
-
4.1 Pre-Installation Inspection
-
4.2 Installation and Adjustment of Insulators for SC Platform
-
4.3 Assembling of SC Platform
-
4.4 Hoisting and Adjustment of SC Platform
-
4.5 Installation of SC Platform Accessories
-
5 Electric Equipment Installation
-
5.1 General Requirements
-
5.2 Capacitor
-
5.3 Metal-Oxide Varistor(MOV)
-
5.4 Spark Gap(GAP)
-
5.5 Damping Device
-
5.6 Optical Fiber Column
-
5.7 Current Transformer(CT),By-Pass Switch and Disconnector
-
5.8 Control and Protection System
-
6 Equipment Installation Specific to TCSC
-
6.1 Thyristor-Controlled Reactor(TCR)
-
6.2 Thyristor Valve Chamber
-
6.3 Voltage Divider
-
6.4 Water Cooling System
-
7 Acceptance of SC Project
-
Explanation of Wording in This Code
-
List of Quoted Standards