DL/T 5142-2012 DL/T 5142-2012 火力发电厂除灰设计技术规程:英文版 - 工标库
由工标库AI生成
查看更多
DL/T 5142-2012 DL/T 5142-2012 火力发电厂除灰设计技术规程:英文版现行
收藏
-
Introduction
-
翻译出版说明
-
National Energy Administration Announcement
-
Foreword
-
1 General Provisions
-
2 Terms
-
3 Pneumatic Ash Handling System
-
3.1 Basic Requirements
-
3.2 Pressure Pneumatic Conveying
-
3.3 Vacuum Conveying
-
3.4 Pneumatic Ash Conveying Pipes
-
3.5 Air Slide
-
3.6 Fly Ash Classifying System
-
4 Hydraulic Ash Handling System
-
4.1 Basic Requirements
-
4.2 Water Supply System for Ash Handling
-
4.3 Hydraulic Ejector
-
4.4 Ash Slurry Trench
-
4.5 Slurry Preparation Equipment
-
4.6 Centrifugal Ash Slurry Pump
-
4.7 Plunger Type Fly Ash Slurry Pump
-
4.8 Dewatering Bin and Clarifying Equipment
-
4.9 Bottom Ash Settlement Pond
-
4.10 Hydraulic Ash Conveying Pipe
-
5 Mechanical Ash Handling System
-
5.1 Basic Requirements
-
5.2 Air-cooled Slag Conveyor
-
5.3 Submerged Scrapper Conveyor
-
5.4 En-masse Scraper Conveyor
-
5.5 Vertical Bucket Elevator
-
5.6 Bucket Conveyor
-
6 Mill Rejects Conveying System
-
6.1 Basic Requirements
-
6.2 Simple Mechanical Conveying
-
6.3 Hydraulic Jet Pump Conveying
-
6.4 Mechanical Conveying
-
7 Air Supply System
-
7.1 Basic Requirements
-
7.2 Air Compressor and Treatment Facilities of Compressed Air
-
7.3 Rotary Blower and Vacuum Pump
-
8 Material Storage and Unloading System
-
8.1 Basic Requirements
-
8.2 Fly Ash Silo and Hopper
-
8.3 Bottom Ash Silo and Mill Rejects Bin
-
8.4 Unloading System and Equipment Selection
-
9 Off-site Transportation System
-
9.1 Basic Requirements
-
9.2 Truck Transportation
-
9.3 Belt Conveyor
-
9.4 Ship Transportation
-
10 Ash Handling System for CFB Boiler
-
10.1 Basic Requirements
-
10.2 Bottom Ash Handling System
-
10.3 Limestone Powder Handling System
-
11 Ash Handling System for Municiple Solid Waste Incineration Power Plant
-
11.1 Basic Requirements
-
11.2 Bottom Ash Handling System
-
11.3 Fly Ash Handling System
-
12 Ash Handling System for Straw Power Plant
-
12.1 Basic Requirements
-
12.2 Mechanical Ash Handling System
-
12.3 Pneumatic Ash Handling System
-
12.4 Ash Storage
-
13 Slime Pipelines Conveying System
-
13.1 Basic Requirements
-
13.2 Piping Conveying System
-
13.3 Equipment Selections
-
13.4 Slime Pump House
-
14 Design Requirements for Relevant Disciplines
-
14.1 Mechanical Discipline
-
14.2 I&C and Electrical Discipline
-
14.3 Civil and Hydraulic Structure Disciplines
-
14.4 Hydraulic and Water Treatment Disciplines
-
14.5 Heating and Ventilation Disciplines
-
14.6 General Plan Discipline
-
Appendix A Calculation of Ash Amount
-
Appendix B Calculation of Mill Rejects Amount
-
Appendix C Density of Some Materials
-
Appendix D Calculation of Reynolds Number
-
Explanation of Wording in this Code
-
List of Quoted Standards